156 tracked projects representing 115,101 MW of announced or built capacity across 23 jurisdictions. 156 carry a current 0–100 delivery health score (higher is healthier), scored across schedule, regulatory, infrastructure, and capital risk — every factor cites its source.

Status Jurisdiction Health score

29 projects

Owners & operators
xAI Colossus 2 (Memphis) US — Rest of US (composite) xAI 1,000 facility total
Operating
82/100
AWS Project Rainier (New Carlisle) US — Rest of US (composite) Amazon Web Services 2,200 facility total
Operating
77/100
Stargate Abilene (Crusoe campus) US — Texas (ERCOT) Crusoe 1,200 facility total
Operating
75.8/100
Meta Stanton Springs / Newton Data Center US — Georgia (Southern/Georgia Power) Meta
Operating
74/100
QTS Atlanta Metro DC1 US — Georgia (Southern/Georgia Power) QTS Data Centers
Operating
69.5/100
Stack Infrastructure NVA02 (Manassas) US — Virginia (PJM/Dominion) STACK Infrastructure 420 it load
Operating
69.5/100
QTS Ashburn 1 (ASH1) US — Virginia (PJM/Dominion) QTS Data Centers 55 it load
Operating
69.5/100
Iron Mountain VA-1 (Manassas) US — Virginia (PJM/Dominion) Iron Mountain
Operating
69.5/100
NEXTDC M3 (West Footscray, Melbourne) Australia NEXTDC
Operating
69.5/100
Microsoft Fairwater Atlanta US — Georgia (Southern/Georgia Power) Microsoft
Operating
64/100
Google Council Bluffs Data Center US — Iowa (MISO) Google
Operating
63.5/100
Cirion BUE1 Buenos Aires Expansion Argentina Cirion Technologies 9 unspecified
Operating
62.5/100
Meta Henrico Data Center (White Oak Technology Park) US — Virginia (PJM/Dominion) Meta Platforms (Facebook)
Operating
62/100
Vantage Data Centers Ashburn I (VA1) US — Virginia (PJM/Dominion) Vantage Data Centers 206 it load
Operating
61.5/100
Switch The Keep Campus (Douglas County) US — Georgia (Southern/Georgia Power) Switch
Operating
61.5/100
Meta (Facebook) Forest City Data Center US — North Carolina (Duke Energy) Meta (Facebook)
Operating
60/100
Google Douglas County Data Center US — Georgia (Southern/Georgia Power) Google
Operating
59.5/100
Google Lenoir Data Center US — North Carolina (Duke Energy) Google
Operating
59.5/100
Microsoft West Des Moines Data Centers US — Iowa (MISO) Microsoft
Operating
58/100
Edged Atlanta ATL01 Campus (Tilford Yard) US — Georgia (Southern/Georgia Power) Edged 168 it load
Operating
58/100
NEXTDC S3 (Sydney) Australia NEXTDC 80 unspecified
Operating
58/100
Digital Edge SEL2 (Incheon) South Korea Digital Edge, SK Ecoplant 36 unspecified
Operating
58/100
Empyrion KR1 Gangnam (Seoul) South Korea Empyrion Digital
Operating
58/100
Google Hanau Data Center Germany Google, GARBE.DC
Operating
57.5/100
Google Waltham Cross Data Centre United Kingdom Google
Operating
56.5/100
AWS New Albany Data Center Campus US — Ohio (AEP Ohio / PJM) Amazon Web Services
Operating
54.5/100
Microsoft Boydton Campus US — Virginia (PJM/Dominion) Microsoft
Operating
54/100
NTT VA6 (Ashburn) US — Virginia (PJM/Dominion) NTT Ltd. 24 it load
Operating
54/100
Apple Maiden Data Center US — North Carolina (Duke Energy) Apple
Operating
52/100