Empyrion KR1 Gangnam (Seoul)

Empyrion KR1 Gangnam (Seoul)

Operating
Confirmed

Jurisdiction: South Korea

224 Yangjae-dong, Seocho-gu — nine stories, 29.4MW IT across 30,714 sqm; first new Gangnam-district DC in over a decade; groundbreaking Jun 2023, opened Jul 2025 (~$400M).

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

58 /100
58/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

60 /100
60/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital staleness decay +10 Empyrion KR1 Gangnam (Seoul) Newest capital evidence is 2025-07-02 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Empyrion KR1 Gangnam (Seoul) Newest regulatory evidence is 2025-07-02 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Capital baseline 40 Empyrion KR1 Gangnam (Seoul) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Infrastructure baseline 70 Empyrion KR1 Gangnam (Seoul) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure interconnection progress +15 Commissioning Power/interconnection milestone "Commissioning" achieved on 2025-07-01 — largest single health event (§B.2.3).
Infrastructure staleness decay -25 Empyrion KR1 Gangnam (Seoul) Newest infrastructure evidence is 2025-07-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Empyrion KR1 Gangnam (Seoul) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Empyrion KR1 Gangnam (Seoul) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Commissioning Milestone "Commissioning" achieved on/ahead of its first announced date (2025-07-01).
Schedule staleness decay -25 Empyrion KR1 Gangnam (Seoul) Newest schedule evidence is 2025-07-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Commissioning

    Achieved

    Commissioning · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Empyrion Digital
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Empyrion Digital · Jul 2, 2025 · backs: actual date, status

    https://empyriondigital.com/empyrion-digital-celebrates-grand-opening-of-kr1-gangnam-data-centre/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Empyrion Digital · relevance 0.90