Compute Institute
Ratings for the physical buildout of AI
Digital Edge SEL2 (Incheon)

Digital Edge SEL2 (Incheon)

Operating
Confirmed

Jurisdiction: South Korea

Bupyeong-gu, Incheon (Seoul metro) — first phase of Digital Edge's 100+MW campus; RFS Oct 16 2024; AI-ready (up to 130kW/rack liquid-cooled, design PUE 1.25); developed with SK Ecoplant.

Capacity
36 MW basis: unspecified
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

58 /100
58/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

60 /100
60/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital staleness decay +10 Digital Edge SEL2 (Incheon) Newest capital evidence is 2024-10-16 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Digital Edge SEL2 (Incheon) Newest regulatory evidence is 2024-10-16 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Capital baseline 40 Digital Edge SEL2 (Incheon) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Infrastructure baseline 70 Digital Edge SEL2 (Incheon) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure interconnection progress +15 Commissioning Power/interconnection milestone "Commissioning" achieved on 2024-10-16 — largest single health event (§B.2.3).
Infrastructure staleness decay -25 Digital Edge SEL2 (Incheon) Newest infrastructure evidence is 2024-10-16 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Digital Edge SEL2 (Incheon) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Digital Edge SEL2 (Incheon) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Commissioning Milestone "Commissioning" achieved on/ahead of its first announced date (2024-10-16).
Schedule staleness decay -25 Digital Edge SEL2 (Incheon) Newest schedule evidence is 2024-10-16 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Commissioning

    Achieved

    Commissioning · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Digital Edge
Developer
SK Ecoplant
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Digital Edge · Oct 16, 2024 · backs: actual date, capacity mw, status

    https://www.digitaledgedc.com/news/digital-edge-announces-availability-of-36mw-data-center-in-south-korea/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Digital Edge · relevance 0.90