Meta Gallatin Data Center

Meta Gallatin Data Center

Operating
Confirmed

Jurisdiction: US — Tennessee (TVA federal power / MLGW & local distributors; non-RTO)

~900 acres, Gallatin (Sumner County) — up to 12 data halls / ~1.5M sq ft; launched Nov 2024; drawing up to ~300MW; Sep 2025 planning permission added a 135,000 sq ft rapid-deployment ('tent') structure paired with off-grid gas (Williams Socrates, 400MW behind-the-meter).

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

58 /100
58/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

60 /100
60/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital staleness decay +10 Meta Gallatin Data Center Newest capital evidence is 2024-11-01 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Meta Gallatin Data Center Newest regulatory evidence is 2024-11-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Capital baseline 40 Meta Gallatin Data Center No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Infrastructure baseline 70 Meta Gallatin Data Center No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure interconnection progress +15 Commissioning Power/interconnection milestone "Commissioning" achieved on 2024-11-01 — largest single health event (§B.2.3).
Infrastructure staleness decay -25 Meta Gallatin Data Center Newest infrastructure evidence is 2024-11-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Meta Gallatin Data Center No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Meta Gallatin Data Center No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Commissioning Milestone "Commissioning" achieved on/ahead of its first announced date (2024-11-01).
Schedule staleness decay -25 Meta Gallatin Data Center Newest schedule evidence is 2024-11-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Commissioning

    Achieved

    Commissioning · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Meta
Owner
DPR Construction
General Contractor
Tennessee Valley Authority
Utility Provider

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Meta Data Centers · Nov 1, 2024 · backs: actual date, status

    https://datacenters.atmeta.com/2024/11/gallatin-we-are-online/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Data Center Dynamics · relevance 0.85

  2. · Meta Data Centers · relevance 0.90

  3. WPLN News · relevance 0.40