NTT VA6 (Ashburn)

NTT VA6 (Ashburn)

Operating
Confirmed

Jurisdiction: US — Virginia (PJM/Dominion)

NTT's 78-acre Ashburn campus, Loudoun County — sixth building, 180,000 sq ft, 24MW critical IT. Broke ground May 2022; Phase 1 substantially complete Aug 2023 (on schedule); buildout through mid-2024. Clark Construction GC.

Capacity
24 MW basis: it load
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

This project has not been scored yet.

Milestones

  1. Groundbreaking

    Achieved

    Groundbreaking · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Clark Construction
General Contractor
NTT Ltd.
Owner

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Data Center Dynamics · Aug 30, 2023 · backs: actual date, capacity mw, status

    https://www.datacenterdynamics.com/en/news/clark-delivers-data-center-to-ntt-in-ashburn-virginia/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Data Center Dynamics

  2. · Clark Construction