Jurisdiction: US — Virginia (PJM/Dominion)
22271 Broderick Dr / 22280 Randolph Dr, Sterling, VA (Loudoun County); 28-acre campus. DC1 operating (55MW), DC2 expansion (22.5MW) coming online Q2 2026.
Methodology prs-v0.1 · computed · trigger: manual
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | QTS Ashburn 1 (ASH1) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Regulatory | baseline | 70 | QTS Ashburn 1 (ASH1) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Infrastructure | baseline | 70 | QTS Ashburn 1 (ASH1) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | QTS Ashburn 1 (ASH1) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
Energization · Expected:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| QTS Data Centers | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
QTS (q.com) · backs: capacity mw, expected date, status
https://q.com/data-centers/ashburn
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
QTS (q.com)