Every build we can see — whether or not we rate it. A record here asserts two things and no more: that the build exists, and where we read about it. Capacity, status and location are reported figures, attributed to their source and never treated as canonical.
When a build earns a primary-source spine we verify it, score it, and it moves to the rated tier — where the number is ours and we stand behind it. How a build gets rated.
builds tracked
rated
markets scored
| Build | Jurisdiction (reported) | Capacity (reported) | State | Source |
|---|---|---|---|---|
| Childress, Texas | US — Texas (ERCOT) | 800 MW | thenextweb.com | |
| Kyle | US — Texas (ERCOT) | 800 MW | DataCenterDynamics (DCD) | |
| Nebius Independence Missouri data center | US — Rest of US (composite) | 800 MW | Data Center Dynamics | |
| Social Circle | US — Georgia (Southern/Georgia Power) | 800 MW | DataCenterDynamics (DCD) | |
| Warrenton, Missouri | US — Texas (ERCOT) | 800 MW | thenextweb.com | |
| Gryfin Project | — | 790 MW | Data Center Dynamics | |
| South Campus Phase 2 Expansion (SBN210) | — | 775 MW | Measured AI (Corey Trinetti) | |
| CyrusOne Fairfield Texas data center campus | US — Texas (ERCOT) | 760 MW | Data Center Dynamics | |
| CyrusOne Freestone County | — | 760 MW | Latitude Media | |
| Eddystone Generating Station | US — Rest of US (composite) | 760 MW | Data Center Knowledge | |
| Cleco 756MW natural gas plant | — | 756 MW | Data Center Dynamics | |
| Ransom Township data center | — | 750 MW | Data Center Dynamics | |
| Palisades nuclear power plant | — | 725 MW | Interesting Engineering | |
| Cambois | — | 720 MW | Data Center Dynamics | |
| Quest Park Data Center | — | 720 MW | Data Center Dynamics | |
| St. Joseph Energy Center | — | 720 MW | Circle of Blue (Water) | |
| Engrida | — | 707 MW | Data Center Dynamics | |
| Barstow | — | 700 MW | Data Center Dynamics | |
| Johor under construction | — | 700 MW | thenextweb.com | |
| Microsoft-Crusoe Abilene Texas | US — Texas (ERCOT) | 700 MW | Data Center Dynamics | |
| Singapore low-carbon data centre park Jurong Island | Singapore | 700 MW | thenextweb.com | |
| Faraday Solar | — | 685 MW | Daily Herald | |
| Aperion Energy Group 684MW data center power project | US — Texas (ERCOT) | 684 MW | Data Center Dynamics | |
| National gas-fired power plants for data centers | US — Rest of US (composite) | 662 MW | Inside Climate News | |
| Portland General Electric Hillsboro GridCARE deployment | US — Rest of US (composite) | 650 MW | pv magazine USA | |
| Switch Tahoe Reno exascale data center | — | 650 MW | Tom’s Hardware | |
| Quantum Clean Energy Project | US — Texas (ERCOT) | 640 MW | POWER Magazine | |
| NYDIG Massena Data Center Expansion | US — Rest of US (composite) | 635 MW | Data Center Dynamics | |
| Onshore wind capacity | — | 629 MW | thenextweb.com | |
| NextDC S7 | — | 612 MW | Data Center Dynamics | |
| Astra North | US — Rest of US (composite) | 600 MW | Data Center Dynamics | |
| Cato | — | 600 MW | Data Centre Review | |
| Duane Arnold Energy Center | — | 600 MW | Data Center Dynamics | |
| East Havering Data Centre Campus (EHDCC) | — | 600 MW | The Guardian | |
| Lumina CloudInfra acquisition | — | 600 MW | thenextweb.com | |
| Nexus - Apex DFW HB1 | — | 600 MW | Data Center Dynamics | |
| Project Tango | — | 600 MW | Inside Climate News | |
| RedNote Inner Mongolia data center campus | — | 600 MW | Data Center Dynamics | |
| YTL Green Data Center Park | — | 600 MW | Data Center Dynamics | |
| North Campus Phase 1 (SBN100) | — | 590 MW | Measured AI (Corey Trinetti) | |
| Ginna Clean Energy Center | — | 576 MW | Interesting Engineering | |
| CDC 555MW US Customer Contract | — | 555 MW | CDC Data Centres | |
| S7 Western Sydney AI Campus | — | 550 MW | The Urban Developer | |
| Seinäjoki campus | — | 550 MW | Capacity Media | |
| SJK01 Phase 1 | — | 550 MW | Data Center Dynamics | |
| Kurri Kurri Data Centre | — | 540 MW | Data Center Dynamics | |
| Rufus | — | 540 MW | Data Centre Review | |
| Microsoft Azure cluster North Rhine-Westphalia | — | 520 MW | Heise Online | |
| RCJM1 | — | 510 MW | Data Center Dynamics | |
| 500 MW facility (Virginia example) | US — Virginia (PJM/Dominion) | 500 MW | Data Center Knowledge |