194 tracked projects representing 117,627 MW of announced or built capacity across 29 jurisdictions. 194 carry a current 0–100 delivery health score (higher is healthier), scored across schedule, regulatory, infrastructure, and capital risk — every factor cites its source.

Status Jurisdiction Health score

3 projects

Owners & operators
Rowan Bauxite I (Quantum Frederick) US — Maryland (BGE / Pepco / Delmarva Power / Potomac Edison — PJM) Rowan Digital Infrastructure 231 it load
Commissioned
59.5/100
Princeton Digital Group JH1 (Sedenak Tech Park) Malaysia — Johor (Johor-Singapore SEZ) Princeton Digital Group 150 unspecified
Commissioned
58/100
Meta Temple Data Center US — Texas (ERCOT) Meta 152 unspecified
Commissioned
55/100