Jurisdiction: Malaysia — Johor (Johor-Singapore SEZ)
Sedenak Tech Park (STeP), Johor — 150MW AI-ready campus on 31 acres acquired from JLand Group; Phase 1 (52MW) delivered in 12 months (Jul 2024); later phases building.
Methodology prs-v0.1 · computed · trigger: scheduled
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | staleness decay | +10 | Princeton Digital Group JH1 (Sedenak Tech Park) | Newest capital evidence is 2024-07-03 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
| Regulatory | staleness decay | -20 | Princeton Digital Group JH1 (Sedenak Tech Park) | Newest regulatory evidence is 2024-07-03 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
| Capital | baseline | 40 | Princeton Digital Group JH1 (Sedenak Tech Park) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | Princeton Digital Group JH1 (Sedenak Tech Park) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Infrastructure | interconnection progress | +15 | Commissioning | Power/interconnection milestone "Commissioning" achieved on 2024-07-01 — largest single health event (§B.2.3). |
| Infrastructure | staleness decay | -25 | Princeton Digital Group JH1 (Sedenak Tech Park) | Newest infrastructure evidence is 2024-07-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
| Regulatory | baseline | 70 | Princeton Digital Group JH1 (Sedenak Tech Park) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | Princeton Digital Group JH1 (Sedenak Tech Park) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Commissioning | Milestone "Commissioning" achieved on/ahead of its first announced date (2024-07-01). |
| Schedule | staleness decay | -25 | Princeton Digital Group JH1 (Sedenak Tech Park) | Newest schedule evidence is 2024-07-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
Commissioning · Actual:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| Princeton Digital Group | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Princeton Digital Group · Jul 3, 2024 · backs: actual date, capacity mw, status
https://princetondg.com/newsroom/princeton-digital-group-delivers-phase-one-of-its-150mw-ai-ready-jh1-campus-in-sedenak-tech-park-johor/
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· Data Center Dynamics · relevance 0.90
· Princeton Digital Group · relevance 0.90