Jurisdiction: US — Texas (ERCOT)
1051 County Road 401, Taylor, TX, approximately 35 miles (56km) northeast of Austin, near the Samsung semiconductor plant. Parcel size is reported inconsistently: DCD (E3) says 220 acres, while the official City of Taylor page (E1) and CBS Austin (E4) say approximately 210 acres (163 acres annexed early 2025 plus ~48 acres in ETJ).
Methodology prs-v0.1 · computed · trigger: manual
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Infrastructure | baseline | 70 | Project Comal | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Capital | baseline | 40 | Project Comal | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Regulatory | baseline | 70 | Project Comal | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | permit granted | +6 | Utility Approval | Permitting milestone "Utility Approval" achieved on 2026-03-26. |
| Schedule | baseline | 80 | Project Comal | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Announcement | Milestone "Announcement" achieved on/ahead of its first announced date (2026-03-26). |
| Schedule | milestone achieved | +5 | Utility Approval | Milestone "Utility Approval" achieved on/ahead of its first announced date (2026-03-26). |
Announcement · Actual:
Utility approval · Actual:
No active constraint observations recorded against this project.
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Data Center Dynamics · Apr 1, 2026 · backs: actual date, capacity mw, status
https://www.datacenterdynamics.com/en/news/360mw-data-center-to-be-built-outside-austin-texas/
Spectrum News · Mar 27, 2026 · backs: actual date, capex usd
https://spectrumlocalnews.com/tx/austin/news/2026/03/27/taylor-approves-land-annexation-for-kdc-data-center
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· Data Center Dynamics
· Spectrum News