Compute Institute
Ratings for the physical buildout of AI
Compass Datacenters Goodyear

Compass Datacenters Goodyear

Construction
Confirmed

Jurisdiction: US — Arizona (APS/SRP)

Goodyear, Arizona (Phoenix suburb).

Capacity
212 MW basis: facility total
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

66 /100
66/100

Methodology prs-v0.1 · computed · trigger: manual

Schedule

80 /100
80/100

Regulatory

70 /100
70/100

Infrastructure

70 /100
70/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Compass Datacenters Goodyear No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory baseline 70 Compass Datacenters Goodyear No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Infrastructure baseline 70 Compass Datacenters Goodyear No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Compass Datacenters Goodyear No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).

Milestones

No milestones recorded for this project yet.

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Compass Datacenters
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Compass Datacenters · backs: capacity mw, status

    https://www.compassdatacenters.com/data-center-markets/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. Compass Datacenters