Compute Institute
Ratings for the physical buildout of AI
Sundt Construction

Sundt Construction

Other

Sundt Construction is a tracked other in the Compute Institute project database holding 1 role across 1 project in 1 jurisdiction (US — Arizona (APS/SRP)), a combined 212 MW of tracked capacity exposure. Every role below is backed by cited source documents.

Exposure

Tracked capacity
212 MW
Evidenced capital
Projects
1
Jurisdictions touched
US — Arizona (APS/SRP)

Tracked MW by project status

Construction
212 MW

Portfolio

Every tracked role this entity holds on a project. Each row derives from cited claims; sources are listed below.

Project
Role
Status
Capacity
Committed capital
Jurisdiction
Compass Datacenters Goodyear
General Contractor
Construction
212 MW US — Arizona (APS/SRP)

Sources & citations

Canonical claims backing this entity record and its project roles, from cited source documents graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Sundt Construction · Dec 12, 2023 · backs: role

    https://www.sundt.com/2023/sundt-team-completes-building-at-compass-datacenters-campus-celebrating-major-milestone-with-toy-drive-for-local-nonprofits/