Entergy Louisiana is a tracked utility in the Compute Institute project database holding 3 roles across 2 projects in 2 jurisdictions (US — Louisiana (Entergy Louisiana / SWEPCO / Cleco — MISO South, LRZ 9; regulator: Louisiana Public Service Commission) and US — Rest of US (composite)), a combined 2,245 MW of tracked capacity exposure. Every role below is backed by cited source documents.
Every tracked role this entity holds on a project. Each row derives from cited claims; sources are listed below.
|
Project
|
Role
|
Status
|
Capacity
|
Committed capital
|
Jurisdiction
|
|---|---|---|---|---|---|
| Meta Hyperion (Richland Parish) | 2,000 MW | — | US — Rest of US (composite) | ||
| Meta Hyperion (Richland Parish) | 2,000 MW | — | US — Rest of US (composite) | ||
| Hut 8 River Bend Data Center Campus | 245 MW | — | US — Louisiana (Entergy Louisiana / SWEPCO / Cleco — MISO South, LRZ 9; regulator: Louisiana Public Service Commission) |
Canonical claims backing this entity record and its project roles, from cited source documents graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Louisiana Economic Development · Dec 17, 2025 · backs: role
https://www.opportunitylouisiana.gov/news/hut-8-selects-southeast-louisiana-as-site-of-10-billion-artificial-intelligence-data-center
Entergy · Dec 6, 2024 · backs: role
https://www.entergy.com/news/entergy-louisiana-power-meta-s-data-center-in-richland-parish
Meta Data Centers · backs: role
https://datacenters.atmeta.com/richland-parish-data-center/