El Paso Electric is a tracked utility in the Compute Institute project database holding 2 roles across 1 project in 1 jurisdiction (US — Texas (ERCOT)), a combined 100 MW of tracked capacity exposure. Every role below is backed by cited source documents.

Exposure

Tracked capacity
100 MW
Evidenced capital
Projects
1
Jurisdictions touched
US — Texas (ERCOT)

Tracked MW by project status

Construction
100 MW

Portfolio

Every tracked role this entity holds on a project. Each row derives from cited claims; sources are listed below.

Project
Role
Status
Capacity
Committed capital
Jurisdiction
Meta El Paso Data Center
Power Supplier
Construction
100 MW US — Texas (ERCOT)
Meta El Paso Data Center
Utility Provider
Construction
100 MW US — Texas (ERCOT)

Sources & citations

Canonical claims backing this entity record and its project roles, from cited source documents graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Meta · Oct 15, 2025 · backs: role

    https://about.fb.com/news/2025/10/metas-new-ai-optimized-data-center-el-paso/

  2. Texas Tribune · Jan 26, 2026 · backs: role

    https://www.texastribune.org/2026/01/26/texas-el-paso-meta-data-center-natural-gas-power-plant/