Vantage Data Centers OH1 (New Albany)

Vantage Data Centers OH1 (New Albany)

Construction
Confirmed

Jurisdiction: US — Ohio (AEP Ohio / PJM)

New Albany, Ohio (Licking County); 70-acre campus, >1.5M sq ft, Vantage's first Midwest project.

Capacity
192 MW basis: facility total
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

53.5 /100
53.5/100

Methodology prs-v0.1 · computed · trigger: manual

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Vantage Data Centers OH1 (New Albany) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Vantage Data Centers OH1 (New Albany) Newest capital evidence is 2024-11-04 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Vantage Data Centers OH1 (New Albany) Newest regulatory evidence is 2024-11-04 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Vantage Data Centers OH1 (New Albany) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Vantage Data Centers OH1 (New Albany) Newest infrastructure evidence is 2024-11-04 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Vantage Data Centers OH1 (New Albany) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Vantage Data Centers OH1 (New Albany) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Groundbreaking Milestone "Groundbreaking" achieved on/ahead of its first announced date (2024-11-04).
Schedule staleness decay -25 Vantage Data Centers OH1 (New Albany) Newest schedule evidence is 2024-11-04 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Groundbreaking

    Achieved

    Groundbreaking · Actual:

  2. Commissioning

    Expected
    1 revision

    Commissioning · Expected:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Vantage Data Centers
Owner
Turner Construction
General Contractor

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Turner Construction · Nov 4, 2024 · backs: actual date, capacity mw, expected date, status

    https://www.turnerconstruction.com/insights/turner-selected-for-2-billion-expansion-project-for-vantage-data-centers

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Turner Construction