Vantage Data Centers DUB1 (Profile Park, Dublin)

Vantage Data Centers DUB1 (Profile Park, Dublin)

Construction
Confirmed

Jurisdiction: Ireland

Profile Park, Grange Castle, ~9 miles south of Dublin. Two phases (32MW + 20MW); on-site 100MVA multi-fuel (HVO/gas) generation plant designed around Ireland's grid-connection constraints.

Capacity
52 MW basis: it load
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

53.5 /100
53.5/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Vantage Data Centers DUB1 (Profile Park, Dublin) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Vantage Data Centers DUB1 (Profile Park, Dublin) Newest capital evidence is 2024-04-29 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Vantage Data Centers DUB1 (Profile Park, Dublin) Newest regulatory evidence is 2024-04-29 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Vantage Data Centers DUB1 (Profile Park, Dublin) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Vantage Data Centers DUB1 (Profile Park, Dublin) Newest infrastructure evidence is 2024-04-29 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Vantage Data Centers DUB1 (Profile Park, Dublin) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Vantage Data Centers DUB1 (Profile Park, Dublin) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2024-04-24).
Schedule staleness decay -25 Vantage Data Centers DUB1 (Profile Park, Dublin) Newest schedule evidence is 2024-04-24 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Vantage Data Centers
Developer
John Sisk & Son
General Contractor
Gas Networks Ireland
Utility Provider

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Vantage Data Centers · Apr 24, 2024 · backs: actual date, capacity mw

    https://vantage-dc.com/news/vantage-data-centers-expands-emea-portfolio-with-first-dublin-campus-featuring-next-generation-energy-solution/

  2. John Sisk & Son · Apr 29, 2024 · backs: status

    https://sisk.com/news/sisk-officially-announced-for-vantage-data-centers-dublin-campus

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · John Sisk & Son · relevance 0.90

  2. · Data Center Dynamics · relevance 0.90

  3. · Vantage Data Centers · relevance 0.90