Jurisdiction: US — North Carolina (Duke Energy)
Kings Mountain, Cleveland County, NC; 300-acre campus, Duke Energy 180MVA on-site substation. Phase I delivery 2026. (Operating T5 @ Charlotte IV, 6MW, on same campus.)
Methodology prs-v0.1 · computed · trigger: manual
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | T5 @ Charlotte II (Kings Mountain) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | T5 @ Charlotte II (Kings Mountain) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | baseline | 70 | T5 @ Charlotte II (Kings Mountain) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | T5 @ Charlotte II (Kings Mountain) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Announcement | Milestone "Announcement" achieved on/ahead of its first announced date (2013-09-13). |
Announcement · Actual:
Commissioning · Expected:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| T5 Data Centers | — | — | |
| Duke Energy | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
T5 Data Centers · Sep 13, 2013 · backs: actual date
https://t5datacenters.com/resources/t5-data-centers-signs-lease-with-financial-services-customer-at-t5kings-mountain-campus/
T5 Data Centers · backs: capacity mw, expected date, status
https://t5datacenters.com/locations/t5-charlotte-ii/
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
T5 Data Centers