Jurisdiction: US — Virginia (PJM/Dominion)
Berry Hill megasite, Pittsylvania County (Southside VA, ~200mi from Ashburn) — 2,990 acres, 30-year build-out, $73.5B minimum commitment (revised ~$100B); APPALACHIAN POWER territory (not Dominion). Performance agreement approved May 2026; phase-1 land (1,000+ acres) must close by Jun 2027; 299MW grid power must be confirmed by end-2028.
Methodology prs-v0.1 · computed · trigger: scheduled
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | Stack Infrastructure Berry Hill Megasite (Pittsylvania) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | Stack Infrastructure Berry Hill Megasite (Pittsylvania) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | baseline | 70 | Stack Infrastructure Berry Hill Megasite (Pittsylvania) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | permit granted | +6 | Utility Approval | Permitting milestone "Utility Approval" achieved on 2026-05-19. |
| Schedule | baseline | 80 | Stack Infrastructure Berry Hill Megasite (Pittsylvania) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Utility Approval | Milestone "Utility Approval" achieved on/ahead of its first announced date (2026-05-19). |
Utility approval · Actual:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| STACK Infrastructure | — | — | |
| Appalachian Power | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Cardinal News · Mar 10, 2026 · backs: actual date
https://cardinalnews.org/2026/03/10/73-billion-project-at-pittsylvania-megasite-would-be-largest-in-southside-history/
Data Center Dynamics · Mar 10, 2026 · backs: status
https://www.datacenterdynamics.com/en/news/stack-commits-735bn-investment-into-data-center-campus-in-berry-hill-virginia/
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· WSET · relevance 0.90
· Data Center Dynamics · relevance 0.95
· Cardinal News · relevance 0.70