Stack Infrastructure Berry Hill Megasite (Pittsylvania)

Stack Infrastructure Berry Hill Megasite (Pittsylvania)

Planned
Probable

Jurisdiction: US — Virginia (PJM/Dominion)

Berry Hill megasite, Pittsylvania County (Southside VA, ~200mi from Ashburn) — 2,990 acres, 30-year build-out, $73.5B minimum commitment (revised ~$100B); APPALACHIAN POWER territory (not Dominion). Performance agreement approved May 2026; phase-1 land (1,000+ acres) must close by Jun 2027; 299MW grid power must be confirmed by end-2028.

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

This project has not been scored yet.

Milestones

  1. Utility Approval

    Achieved

    Utility approval · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
STACK Infrastructure
Developer
Appalachian Power
Utility Provider

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Cardinal News · Mar 10, 2026 · backs: actual date

    https://cardinalnews.org/2026/03/10/73-billion-project-at-pittsylvania-megasite-would-be-largest-in-southside-history/

  2. Data Center Dynamics · Mar 10, 2026 · backs: status

    https://www.datacenterdynamics.com/en/news/stack-commits-735bn-investment-into-data-center-campus-in-berry-hill-virginia/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · WSET

  2. · Data Center Dynamics

  3. · Cardinal News