Security Land and Development Woodlawn Data Center

Security Land and Development Woodlawn Data Center

Planned
Probable

Jurisdiction: US — Maryland (BGE / Pepco / Delmarva Power / Potomac Edison — PJM)

1500 Woodlawn Drive area, Woodlawn, Baltimore County, MD — 42-acre site; five acres to be donated to BGE for a new substation. Construction targeted June-July 2026; end user undisclosed.

Capacity
150 MW basis: unspecified
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

58 /100
58/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

55 /100
55/100

Regulatory

70 /100
70/100

Infrastructure

70 /100
70/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Security Land and Development Woodlawn Data Center No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory baseline 70 Security Land and Development Woodlawn Data Center No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Infrastructure baseline 70 Security Land and Development Woodlawn Data Center No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Security Land and Development Woodlawn Data Center No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule staleness decay -25 Security Land and Development Woodlawn Data Center Newest schedule evidence is 2026-01-05 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

No milestones recorded for this project yet.

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Security Land and Development
Developer
BGE
Utility Provider

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. WYPR · Jan 5, 2026 · backs: status

    https://www.wypr.org/wypr-news/2026-01-05/one-year-data-center-moratorium-proposed-in-baltimore-county

  2. WMAR-2 News · Dec 3, 2025 · backs: capacity mw

    https://www.wmar2news.com/news/region/baltimore-county/controversial-proposed-data-center-up-for-debate-in-woodlawn

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · WYPR · relevance 0.70

  2. · Patch (Towson) · relevance 0.85

  3. · WMAR-2 News · relevance 0.70