Jurisdiction: US — Maryland (BGE / Pepco / Delmarva Power / Potomac Edison — PJM)
Former 2,100-acre Alcoa Eastalco Works site near Buckeystown/Adamstown, Frederick County, MD. Master data-center campus hosting Aligned and Rowan sub-projects; 40-mile fiber run to Loudoun County VA. Catellus (TPG) is lead developer after Quantum Loophole's Dec 2024 exit.
Methodology prs-v0.1 · computed · trigger: scheduled
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | Quantum Frederick Park (master campus) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | Quantum Frederick Park (master campus) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | baseline | 70 | Quantum Frederick Park (master campus) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | Quantum Frederick Park (master campus) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Announcement | Milestone "Announcement" achieved on/ahead of its first announced date (2021-06-28). |
| Schedule | staleness decay | -25 | Quantum Frederick Park (master campus) | Newest schedule evidence is 2021-06-28 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
Announcement · Actual:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| Catellus Development Corporation | — | — | |
| Quantum Loophole | — | — | |
| TPG Real Estate Partners | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Maryland Department of Commerce · Jun 28, 2021 · backs: actual date
https://commerce.maryland.gov/media/maryland-commerce-frederick-county-announce-purchase-of-former-alcoa-eastalco-site
Catellus Development Corporation · backs: status
https://www.catellus.com/hyperscale-data-center-campus
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· Maryland Department of Commerce · relevance 0.30
Catellus Development Corporation · relevance 0.30