Jurisdiction: US — Georgia (Southern/Georgia Power)
615-acre Main Campus along GA-54, Fayetteville, Fayette County (~30mi SW of Atlanta) + 313-acre East Campus expansion (928 acres total). Up to 16 buildings / 6.6M+ sq ft; 4 operational + 5 under construction (May 2026); ~8,000 peak construction workers. CAMPUS/developer record — Microsoft's Fairwater buildings inside this campus have their own record (microsoft-fairwater-atlanta).
Methodology prs-v0.1 · computed · trigger: scheduled
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | QTS Fayetteville Campus (Project Excalibur) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | QTS Fayetteville Campus (Project Excalibur) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Infrastructure | interconnection progress | +15 | Commissioning | Power/interconnection milestone "Commissioning" achieved on 2025-10-01 — largest single health event (§B.2.3). |
| Infrastructure | staleness decay | -25 | QTS Fayetteville Campus (Project Excalibur) | Newest infrastructure evidence is 2025-10-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
| Regulatory | baseline | 70 | QTS Fayetteville Campus (Project Excalibur) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | QTS Fayetteville Campus (Project Excalibur) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Commissioning | Milestone "Commissioning" achieved on/ahead of its first announced date (2025-10-01). |
| Schedule | staleness decay | -25 | QTS Fayetteville Campus (Project Excalibur) | Newest schedule evidence is 2025-10-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
Commissioning · Actual:
No active constraint observations recorded against this project.
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Atlanta Journal-Constitution · May 1, 2026 · backs: actual date, status
https://www.ajc.com/business/2026/05/the-data-center-boom-is-transforming-georgia-some-residents-could-lose-their-land/
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· The Citizen
· Atlanta Journal-Constitution
· Data Center Dynamics