Project Gravity (Archbald / Gouldsboro Data Center Campus)

Project Gravity (Archbald / Gouldsboro Data Center Campus)

Stalled
Confirmed

Jurisdiction: US — Pennsylvania (PJM)

Lackawanna County — proposed ~1,000-acre campus along I-380 (Clifton Beach Road area) plus 186 acres in Archbald Borough. Developer 1778 Rich Pike LLC. No tenant; removed from the PA Permit Fast Track program May 2026.

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

35 /100
35/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

80 /100
80/100

Regulatory

70 /100
70/100

Infrastructure

70 /100
70/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Project Gravity (Archbald / Gouldsboro Data Center Campus) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory baseline 70 Project Gravity (Archbald / Gouldsboro Data Center Campus) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Infrastructure baseline 70 Project Gravity (Archbald / Gouldsboro Data Center Campus) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Project Gravity (Archbald / Gouldsboro Data Center Campus) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule hard cap -31 Project Gravity (Archbald / Gouldsboro Data Center Campus) Hard cap "status_stalled" (health ≤ 35): project status is stalled. [binding]

Milestones

No milestones recorded for this project yet.

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
1778 Rich Pike LLC
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. WVIA · May 1, 2026 · backs: status

    https://www.wvia.org/news/local/2026-05-01/fast-track-no-more-pa-kicks-archbald-data-center-campus-off-permit-program

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · WVIA

  2. · Data Center Dynamics