Compute Institute
Ratings for the physical buildout of AI
Project Aggie (College Station)

Project Aggie (College Station)

Cancelled
Confirmed

Jurisdiction: US — Texas (ERCOT)

Approximately 200 acres along Corporate Parkway and Midtown Drive in the Midtown Business Park, College Station, Brazos County, Texas (near Costco / Midtown area).

Capacity
600 MW basis: unspecified
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

10 /100
10/100

Methodology prs-v0.1 · computed · trigger: manual

Schedule

60 /100
60/100

Regulatory

51 /100
51/100

Infrastructure

50 /100
50/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Project Aggie (College Station) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Infrastructure baseline 70 Project Aggie (College Station) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Project Aggie (College Station) Newest infrastructure evidence is 2025-09-12 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Project Aggie (College Station) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Regulatory permit granted +6 Utility Approval Permitting milestone "Utility Approval" achieved on 2025-09-11.
Regulatory staleness decay -25 Project Aggie (College Station) Newest regulatory evidence is 2025-09-11 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Schedule baseline 80 Project Aggie (College Station) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Utility Approval Milestone "Utility Approval" achieved on/ahead of its first announced date (2025-09-11).
Schedule staleness decay -25 Project Aggie (College Station) Newest schedule evidence is 2025-09-11 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Schedule hard cap -37.75 Project Aggie (College Station) Hard cap "status_cancelled" (health ≤ 10): project status is cancelled. [binding]

Milestones

  1. Announcement

    Expected
    1 revision

    Announcement · Expected:

  2. Utility Approval

    Achieved

    Utility approval · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Priority Power Management, LLC
Developer
PPM Data LLC
Owner
I Squared Capital
Investor
Brandon Schwertner
Developer
City of College Station
Government Partner

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. DatacenterDynamics · Sep 9, 2025 · backs: capacity mw, expected date

    https://www.datacenterdynamics.com/en/news/600mw-data-center-campus-proposed-in-texas/

  2. DatacenterDynamics · Sep 12, 2025 · backs: actual date, status

    https://www.datacenterdynamics.com/en/news/college-station-texas-rejects-land-sale-for-data-center/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · DatacenterDynamics

  2. · KBTX

  3. · DatacenterDynamics