NTT Grove at Gainesville Campus (VA10-VA13)

NTT Grove at Gainesville Campus (VA10-VA13)

Construction
Confirmed

Jurisdiction: US — Virginia (PJM/Dominion)

14210/14300 John Marshall Highway, Gainesville, Prince William County — NTT's largest planned North American campus: 4 buildings, 2M sq ft, 336MW target. VA10 (84MW critical IT) operational Nov 2023; VA11-13 building out. $257.4M land from Lerner Enterprises (2022).

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

56.5 /100
56.5/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

60 /100
60/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital staleness decay +10 NTT Grove at Gainesville Campus (VA10-VA13) Newest capital evidence is 2022-06-15 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 NTT Grove at Gainesville Campus (VA10-VA13) Newest regulatory evidence is 2022-06-15 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Capital baseline 40 NTT Grove at Gainesville Campus (VA10-VA13) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Infrastructure baseline 70 NTT Grove at Gainesville Campus (VA10-VA13) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure interconnection progress +15 Commissioning Power/interconnection milestone "Commissioning" achieved on 2023-11-01 — largest single health event (§B.2.3).
Infrastructure staleness decay -25 NTT Grove at Gainesville Campus (VA10-VA13) Newest infrastructure evidence is 2023-11-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 NTT Grove at Gainesville Campus (VA10-VA13) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 NTT Grove at Gainesville Campus (VA10-VA13) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Commissioning Milestone "Commissioning" achieved on/ahead of its first announced date (2023-11-01).
Schedule staleness decay -25 NTT Grove at Gainesville Campus (VA10-VA13) Newest schedule evidence is 2023-11-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Commissioning

    Achieved

    Commissioning · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
NTT Global Data Centers
Developer
Lerner Enterprises
Owner

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Lerner Enterprises · Jun 15, 2022 · backs: status

    https://lerner.com/news/ntt-expanding-data-center-portfolio-with-257m-land-buy-in-prince-william-county-from-lerner/

  2. Data Center Dynamics · Jun 15, 2022 · backs: actual date

    https://www.datacenterdynamics.com/en/news/ntt-plans-336mw-campus-in-gainesville-virginia/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Lerner Enterprises · relevance 0.90

  2. · NTT · relevance 0.90