Jurisdiction: US — Texas (ERCOT)
2,000-acre site between Highway 171 and County Road 3369 on the outskirts of Hubbard, Hill County, Texas.
Methodology prs-v0.1 · computed · trigger: manual
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | Nexus Data Center (Hubbard) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | Nexus Data Center (Hubbard) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | baseline | 70 | Nexus Data Center (Hubbard) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | Nexus Data Center (Hubbard) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Announcement | Milestone "Announcement" achieved on/ahead of its first announced date (2025-11-20). |
| Schedule | staleness decay | -25 | Nexus Data Center (Hubbard) | Newest schedule evidence is 2025-12-02 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
Announcement · Actual:
Energization · Expected:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| Nexus Data Centers | — | — | |
| AirJoule Technologies | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
AirJoule Technologies (GlobeNewswire) · Dec 2, 2025 · backs: expected date
https://www.globenewswire.com/news-release/2025/12/02/3197885/0/en/AirJoule-Technologies-Identifies-Nexus-Data-Centers-as-AI-Hyperscale-Developer-and-Advances-Existing-MOU-Toward-First-Deployment-of-Onsite-Water-Purchase-Agreement-Using-Waste-Heat.html
Data Center Dynamics · Dec 3, 2025 · backs: capacity mw
https://www.datacenterdynamics.com/en/news/600mw-natural-gas-powered-data-center-campus-proposed-in-hubbard-texas/
Hillsboro Reporter · Nov 27, 2025 · backs: actual date
https://hillsbororeporter.com/nexus-lays-out-hubbard-data-center-plan-p31318-54.htm
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· Data Center Dynamics