Ratings for the physical buildout of AI
Microsoft Grange Castle Campus (DUB14/DUB15)

Microsoft Grange Castle Campus (DUB14/DUB15)

Permitted
Confirmed

Jurisdiction: Ireland

Grange Castle Business Park, Dublin — DUB14/DUB15 extend Microsoft's long-running campus (est. 2009, its first Irish DC), west of DUB9/10/12/13. 170MW on-site gas generation permitted (grid-independence workaround).

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

51 /100
51/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

55 /100
55/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Microsoft Grange Castle Campus (DUB14/DUB15) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Microsoft Grange Castle Campus (DUB14/DUB15) Newest capital evidence is 2022-02-15 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Microsoft Grange Castle Campus (DUB14/DUB15) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Microsoft Grange Castle Campus (DUB14/DUB15) Newest infrastructure evidence is 2022-02-15 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Microsoft Grange Castle Campus (DUB14/DUB15) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Regulatory staleness decay -20 Microsoft Grange Castle Campus (DUB14/DUB15) Newest regulatory evidence is 2022-02-15 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Schedule baseline 80 Microsoft Grange Castle Campus (DUB14/DUB15) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule staleness decay -25 Microsoft Grange Castle Campus (DUB14/DUB15) Newest schedule evidence is 2022-02-15 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

No milestones recorded for this project yet.

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Microsoft
Owner

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. NBCO (Ireland) · Feb 15, 2022 · backs: status

    https://www.nbco.localgov.ie/en/bcms/notice/dub-14-dub-15-cab-water-treatment-building-and-sprinkler-pump-room

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Microsoft · relevance 0.70

  2. · The Register · relevance 0.90

  3. · NBCO (Ireland) · relevance 0.70