Confirmed

Jurisdiction: US — Minnesota (Xcel / MISO)

UMore Park, Rosemount, Dakota County, Minnesota; 715,000 sq ft, >$800M, LEED Gold. Minnesota's first hyperscale DC. Built by Mortenson.

Capacity
GPUs (est.)
Capex
$0.8B
Announced
Mar 14, 2024
Target operational

Delivery health score

51 /100
51/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Infrastructure hard cap 0 Meta Rosemount Data Center Hard cap "missing_interconnection" (health ≤ 55, §B.3): no power-category milestone on file 18+ months after announcement (2024-03-14). [triggered, not binding]
Capital baseline 40 Meta Rosemount Data Center No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Meta Rosemount Data Center Newest capital evidence is 2024-03-16 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Meta Rosemount Data Center Newest regulatory evidence is 2024-03-16 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Meta Rosemount Data Center No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Meta Rosemount Data Center Newest infrastructure evidence is 2024-03-16 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Meta Rosemount Data Center No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Meta Rosemount Data Center No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2024-03-14).
Schedule staleness decay -25 Meta Rosemount Data Center Newest schedule evidence is 2024-03-14 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Meta
Owner
Xcel Energy
Utility Provider
Mortenson
General Contractor

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Meta Data Centers Blog · Mar 14, 2024 · backs: actual date

    https://datacenters.atmeta.com/2024/03/hello-rosemount/

  2. Minnesota Governor's Office · Mar 14, 2024 · backs: announced date, capex usd, status

    https://mn.gov/governor/newsroom/press-releases/?id=1055-614120

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Data Center Dynamics · relevance 0.95

  2. · Meta Data Centers Blog · relevance 0.70

  3. · Minnesota Governor's Office · relevance 0.90

  4. Xcel Energy Stories · relevance 0.85

  5. mn.gov · relevance 0.90