Eneus Energy Cameron County data center

Eneus Energy Cameron County data center

Announced
Probable

Jurisdiction: US — Texas (ERCOT)

Approximately 1,785-acre site in Cameron County, Texas, near (east of) Valley International Airport, in the Harlingen area of the Rio Grande Valley.

Capacity
2,000 MW basis: unspecified
GPUs (est.)
Capex
$0.0B
Announced
Target operational

Delivery health score

60.5 /100
60.5/100

Methodology prs-v0.1 · computed · trigger: manual

Schedule

65 /100
65/100

Regulatory

76 /100
76/100

Infrastructure

70 /100
70/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Infrastructure baseline 70 Eneus Energy Cameron County data center No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Capital baseline 40 Eneus Energy Cameron County data center No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory baseline 70 Eneus Energy Cameron County data center No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Regulatory permit granted +6 Utility Approval Permitting milestone "Utility Approval" achieved on 2025-10-01.
Schedule baseline 80 Eneus Energy Cameron County data center No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2025-07-01).
Schedule milestone achieved +5 Utility Approval Milestone "Utility Approval" achieved on/ahead of its first announced date (2025-10-01).
Schedule staleness decay -25 Eneus Energy Cameron County data center Newest schedule evidence is 2025-10-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

  2. Utility Approval

    Achieved

    Utility approval · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Eneus Energy
Developer
RGV Property Group
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Eneus Energy · backs: capacity mw, capex usd, status

    https://eneusenergy.com/harlingen

  2. Data Center Dynamics · Feb 5, 2026 · backs: actual date

    https://www.datacenterdynamics.com/en/news/2gw-data-center-could-be-developed-in-cameron-county-texas/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Hoodline

  2. · Data Center Dynamics

  3. Eneus Energy