DC BLOX Atlanta West

DC BLOX Atlanta West

Construction
Confirmed

Jurisdiction: US — Georgia (Southern/Georgia Power)

Douglas County, Georgia (Atlanta West). 120MW initial + 80MW expansion.

Capacity
120 MW basis: it load
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

51 /100
51/100

Methodology prs-v0.1 · computed · trigger: manual

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 DC BLOX Atlanta West No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory staleness decay -20 DC BLOX Atlanta West Newest regulatory evidence is 2025-08-11 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 DC BLOX Atlanta West No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 DC BLOX Atlanta West Newest infrastructure evidence is 2025-08-11 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 DC BLOX Atlanta West No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 DC BLOX Atlanta West No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2025-08-11).
Schedule staleness decay -25 DC BLOX Atlanta West Newest schedule evidence is 2025-08-11 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

  2. Energization

    Expected
    1 revision

    Energization · Expected:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
DC BLOX
Developer
ING Capital LLC
Lender
Mizuho Bank, Ltd
Lender
Natixis Corporate & Investment Banking
Lender

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. DC BLOX · Aug 11, 2025 · backs: actual date, capacity mw, expected date, status

    https://www.dcblox.com/dcblox-secures-1-15-billion-green-loan-atlanta-data-center-campus-development/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · DC BLOX