Jurisdiction: US — Texas (ERCOT)
96-acre site at 2955 Francis Harris Lane with a New Braunfels mailing address, but outside the city limits of New Braunfels and San Marcos; site straddles Hays and Guadalupe County jurisdictions, between Austin and San Antonio. Lat/lng not given in sources.
Methodology prs-v0.1 · computed · trigger: manual
Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.
|
Dimension
|
Factor
|
Contribution
|
Cites
|
Narrative
|
|---|---|---|---|---|
| Capital | baseline | 40 | CloudBurst Data Center (New Braunfels) | No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4). |
| Infrastructure | baseline | 70 | CloudBurst Data Center (New Braunfels) | No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines). |
| Regulatory | baseline | 70 | CloudBurst Data Center (New Braunfels) | No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines). |
| Schedule | baseline | 80 | CloudBurst Data Center (New Braunfels) | No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines). |
| Schedule | milestone achieved | +5 | Groundbreaking | Milestone "Groundbreaking" achieved on/ahead of its first announced date (2025-11-05). |
| Schedule | staleness decay | -25 | CloudBurst Data Center (New Braunfels) | Newest schedule evidence is 2025-11-05 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information). |
Groundbreaking · Actual:
Energization · Expected:
No active constraint observations recorded against this project.
|
Entity
|
Role
|
Ownership
|
Committed capital
|
|---|---|---|---|
| CloudBurst Data Centers | — | — | |
| CloudBurst Data Centers | — | — | |
| Evolve Holdings | — | — | |
| Energy Transfer | — | — |
Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.
Evolve Holdings · Nov 5, 2025 · backs: actual date, capacity mw, expected date, status
https://evolveincorporated.com/company-news/cloudburst-and-evolve-break-ground-on-1-2gw-flagship-ai-data-center-campus-incentral-texas
Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.
· Data Center Dynamics
· Evolve Holdings
· Community Impact