Amazon Becker Data Center (Sherco Site)

Amazon Becker Data Center (Sherco Site)

Stalled
Confirmed

Jurisdiction: US — Minnesota (Xcel / MISO)

348-acre parcel in Becker, Sherburne County, MN (former Xcel Sherco coal site). SUSPENDED May 2025 after MN eliminated the DC electricity sales-tax exemption; land retained.

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

35 /100
35/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Amazon Becker Data Center (Sherco Site) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Amazon Becker Data Center (Sherco Site) Newest capital evidence is 2025-05-23 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory staleness decay -20 Amazon Becker Data Center (Sherco Site) Newest regulatory evidence is 2025-05-23 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Amazon Becker Data Center (Sherco Site) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Amazon Becker Data Center (Sherco Site) Newest infrastructure evidence is 2025-05-23 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Amazon Becker Data Center (Sherco Site) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Amazon Becker Data Center (Sherco Site) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2024-11-11).
Schedule hard cap -18.5 Amazon Becker Data Center (Sherco Site) Hard cap "status_stalled" (health ≤ 35): project status is stalled. [binding]
Schedule staleness decay -25 Amazon Becker Data Center (Sherco Site) Newest schedule evidence is 2024-11-11 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Xcel Energy
Utility Provider
Amazon Data Services
Owner

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. MPR News · May 23, 2025 · backs: status

    https://www.mprnews.org/story/2025/05/23/amazon-pulls-back-on-plans-for-large-data-center-in-becker

  2. Data Center Dynamics · Nov 11, 2024 · backs: actual date

    https://www.datacenterdynamics.com/en/news/amazon-buys-350-acre-parcel-in-becker-minnesota-for-data-center/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · MPR News · relevance 0.90

  2. · KNSI Radio · relevance 0.90

  3. · Data Center Dynamics · relevance 0.90

  4. Minnesota House of Representatives · relevance 0.70