Microsoft Southeast Asia 3 Region (Johor Bahru)

Microsoft Southeast Asia 3 Region (Johor Bahru)

Announced
Probable

Jurisdiction: Malaysia — Johor (Johor-Singapore SEZ)

Johor Bahru area (land assemblies: Kulai 123ac, Tebrau 138.5ac, Nusa Cemerlang 22.5ac per 2024-2025 acquisitions) — Microsoft's second Malaysia cloud region, revealed Oct 2025 under the 2024 $2.2B commitment; no launch date; zero-water closed-loop cooling design.

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

47.5 /100
47.5/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

50 /100
50/100

Infrastructure

50 /100
50/100

Capital

40 /100
40/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Microsoft Southeast Asia 3 Region (Johor Bahru) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Regulatory staleness decay -20 Microsoft Southeast Asia 3 Region (Johor Bahru) Newest regulatory evidence is 2025-10-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Microsoft Southeast Asia 3 Region (Johor Bahru) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Microsoft Southeast Asia 3 Region (Johor Bahru) Newest infrastructure evidence is 2025-10-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Microsoft Southeast Asia 3 Region (Johor Bahru) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Schedule baseline 80 Microsoft Southeast Asia 3 Region (Johor Bahru) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Announcement Milestone "Announcement" achieved on/ahead of its first announced date (2025-10-01).
Schedule staleness decay -25 Microsoft Southeast Asia 3 Region (Johor Bahru) Newest schedule evidence is 2025-10-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Announcement

    Achieved

    Announcement · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Microsoft
Developer

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Microsoft Source Asia · Oct 1, 2025 · backs: status

    https://news.microsoft.com/source/asia/features/microsoft-to-expand-cloud-region-in-johor-bahru-empowering-southeast-asias-ai-transformation/

  2. Data Center Dynamics · Nov 1, 2025 · backs: actual date

    https://www.datacenterdynamics.com/en/news/microsoft-details-plans-for-cloud-region-in-johor-malaysia/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Microsoft Source Asia · relevance 0.70

  2. · Microsoft (APAC) · relevance 0.70