Bridge Data Centres MY07 (Ulu Tiram)

Bridge Data Centres MY07 (Ulu Tiram)

Construction
Confirmed

Jurisdiction: Malaysia — Johor (Johor-Singapore SEZ)

Johor Ulu Tiram (land assembled in Mukim of Plentong, 2024: 48ac + 20ac) — Bridge's second Johor hyperscale campus; 400MW TNB Electricity Supply Agreement (Dec 2024, 'Malaysia's fastest ESA delivery' per reporting) incl. CRESS green-energy framework with TNB Renewables.

Capacity
GPUs (est.)
Capex
Announced
Target operational

Delivery health score

53.6 /100
53.6/100

Methodology prs-v0.1 · computed · trigger: scheduled

Schedule

60 /100
60/100

Regulatory

51 /100
51/100

Infrastructure

50 /100
50/100

Capital

50 /100
50/100

Why this score — factor breakdown

Each factor below contributed to the current score. Contributions are rubric weights from methodology prs-v0.1; every factor cites the record it is derived from.

Dimension
Factor
Contribution
Cites
Narrative
Capital baseline 40 Bridge Data Centres MY07 (Ulu Tiram) No committed capital evidenced on any entity role — announcement-only anchor region (§B.2.4).
Capital staleness decay +10 Bridge Data Centres MY07 (Ulu Tiram) Newest capital evidence is 2024-11-30 (freshness window 12 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Infrastructure baseline 70 Bridge Data Centres MY07 (Ulu Tiram) No-adverse-evidence infrastructure baseline (disclosed config, scoring.prs.baselines).
Infrastructure staleness decay -20 Bridge Data Centres MY07 (Ulu Tiram) Newest infrastructure evidence is 2024-11-30 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Regulatory baseline 70 Bridge Data Centres MY07 (Ulu Tiram) No-adverse-evidence regulatory baseline (disclosed config, scoring.prs.baselines).
Regulatory permit granted +6 Utility Approval Permitting milestone "Utility Approval" achieved on 2024-12-01.
Regulatory staleness decay -25 Bridge Data Centres MY07 (Ulu Tiram) Newest regulatory evidence is 2024-12-01 (freshness window 9 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).
Schedule baseline 80 Bridge Data Centres MY07 (Ulu Tiram) No-adverse-evidence schedule baseline (disclosed config, scoring.prs.baselines).
Schedule milestone achieved +5 Utility Approval Milestone "Utility Approval" achieved on/ahead of its first announced date (2024-12-01).
Schedule staleness decay -25 Bridge Data Centres MY07 (Ulu Tiram) Newest schedule evidence is 2024-12-01 (freshness window 6 months) — score drifts one rubric level toward the stage-default prior of 50 (§B.4: silence is information).

Milestones

  1. Utility Approval

    Achieved

    Utility approval · Actual:

Constraint observations

No active constraint observations recorded against this project.

Entities & roles

Entity
Role
Ownership
Committed capital
Bridge Data Centres
Developer
Tenaga Nasional Berhad
Utility Provider

Sources & citations

Every substantive field on this record is backed by a canonical claim from a cited source document, graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. W.Media · Nov 30, 2024 · backs: actual date, status

    https://w.media/tnb-and-bridge-data-centres-ink-400mw-power-deal-to-boost-malaysias-digital-hub-status/

Signals

Recent ingested source documents linked to this project via extracted claims or triage mentions, newest first.

  1. · Data Center Dynamics · relevance 0.90

  2. · W.Media · relevance 0.90