Compute Institute
Ratings for the physical buildout of AI
We Energies (WEC Energy Group)

We Energies (WEC Energy Group)

Utility

We Energies (WEC Energy Group) is a tracked utility in the Compute Institute project database holding 4 roles across 2 projects in 1 jurisdiction (US — Rest of US (composite)), a combined 902 MW of tracked capacity exposure. Every role below is backed by cited source documents.

Also known as:
We Energies

Exposure

Tracked capacity
902 MW
Evidenced capital
Projects
2
Jurisdictions touched
US — Rest of US (composite)

Tracked MW by project status

Construction
902 MW
Energized
0 MW

Portfolio

Every tracked role this entity holds on a project. Each row derives from cited claims; sources are listed below.

Project
Role
Status
Capacity
Committed capital
Jurisdiction
Stargate Wisconsin - Vantage Lighthouse (Port Washington)
Power Supplier
Construction
902 MW US — Rest of US (composite)
Stargate Wisconsin - Vantage Lighthouse (Port Washington)
Utility Provider
Construction
902 MW US — Rest of US (composite)
Microsoft Fairwater (Mount Pleasant)
Power Supplier
Energized
US — Rest of US (composite)
Microsoft Fairwater (Mount Pleasant)
Utility Provider
Energized
US — Rest of US (composite)

Sources & citations

Canonical claims backing this entity record and its project roles, from cited source documents graded on the E1 (strongest) – E5 (weakest) evidence ladder.

  1. Microsoft On the Issues · Sep 18, 2025 · backs: role

    https://blogs.microsoft.com/on-the-issues/2025/09/18/made-in-wisconsin-the-worlds-most-powerful-ai-datacenter/

  2. Vantage Data Centers · Oct 22, 2025 · backs: role

    https://vantage-dc.com/news/openai-oracle-and-vantage-data-centers-announce-stargate-data-center-site-in-wisconsin/